Geological Survey of Xiangshan Tuici Offshore Wind Farm Project of CGNPC Completed
Release date:2022-06-20 08:48 browsing:

On June 9th, geological survey (detailed survey) of CGNPC Xiangshan Tuci Offshore Wind Farm Project was successfully completed. The survey results show that the stratum structure is normal, which means that the geology of Tuci Offshore Wind Power meets the construction conditions of fan pile foundation.


Located in the northeast sea of our county, the Project is the second offshore wind power project in Ningbo after State Grid Xiangshan Offshore Wind Farm (phase I). The project plans to deploy 38 wind turbines with a single capacity of 8 MW, with a total investment of 3.3 billion yuan. After the completion of the project of the annual power grid 840 million KWH will reduce all kinds of harmful gases and soot emissions of about 570,000 tons, contributing to the adjustment of local industrial structure, which has good social and comprehensive economic benefits.


After 50 days’ exploration operation, 38 static drilling holes and 16 drilling holes were completed in total. The data of stratum structure and geological friction force have been mainly obtained to ensure the safety of subsequent pile foundation construction.